Cost of Capital
30 original practice MCQs, 2 marks each. Practice and separate-test stems differ. Standalone drills across the chapter, with a separate case-based test pack.
Original practice, not official ICAI questions or suggested answers. Scores are temporary and not synced to Study Hub. Contract/current-rule/accounting/tax boundaries are included in the review pack.
Not scored yet.
FM-C04-P001 · 2 marksNo cash dividend is planned this year. Equity finance therefore costs what?
Explanation
Correct answer A: It still has an investor opportunity cost.
Forgone alternatives and expected investor returns matter.
FM-C04-P002 · 2 marksCoupon Rs 12, net proceeds Rs 92, coupon tax 30% fully usable. After-tax perpetual cost?
Explanation
Correct answer A: 9.13%.
12 x.7/92=9.1304%.
FM-C04-P003 · 2 marksExisting perpetual coupon Rs 10, market price Rs 80, tax 25%. Current cost?
Explanation
Correct answer D: 9.375%.
10 x.75/80=.09375.
FM-C04-P004 · 2 marksCoupon 8, net 100, no deductible interest or usable tax shield in case. Cost?
Explanation
Correct answer C: 8%.
No shield is assumed, so 8/100.
FM-C04-P005 · 2 marksNP 90, RV 100, n 5, coupon 10, coupon-only tax 30%. Approx cost using average capital?
Explanation
Correct answer D: 9.4737%.
(7+2)/95; redemption difference is not deductible here.
FM-C04-P006 · 2 marksReceive 70 now and repay 100 in 3 years, no tax. Exact annual cost?
Explanation
Correct answer B: 12.6248%.
(100/70)^(1/3)-1.
FM-C04-P007 · 2 marksWhy can bullet-redemption approximation fail on annually repaid principal?
Explanation
Correct answer C: Cash dates and declining principal differ.
Discount actual scheduled payments.
FM-C04-P008 · 2 marksDividend 9, net 94, no deduction. Perpetual preference cost?
Explanation
Correct answer C: 9.5745%.
9/94; no tax shield under case.
FM-C04-P009 · 2 marksDividend 8, NP 95, RV 105, n 4, no tax. Average-capital approximation?
Explanation
Correct answer C: 10.5%.
(8+10/4)/100=10.5%; exact IRR differs.
FM-C04-P010 · 2 marksD0=4, g 5%. Next expected dividend?
Explanation
Correct answer D: Rs 4.20.
4 x 1.05.
FM-C04-P011 · 2 marksD1=4.2, issue 80, flotation 4, g 5%. New equity cost?
Explanation
Correct answer C: 10.5263%.
4.2/76+.05.
FM-C04-P012 · 2 marksIssue 100, one-time float 5%, D1=5, g 4%. New cost?
Explanation
Correct answer B: 9.2632%.
5/95+.04.
FM-C04-P013 · 2 marksDividend 2 becomes 2.662 over 3 years. Compound growth?
Explanation
Correct answer D: 10%.
(2.662/2)^(1/3)-1.
FM-C04-P014 · 2 marksRetention 40%, return on reinvestment 15%. Stable g?
Explanation
Correct answer B: 6%.
b*r=.4 x.15.
FM-C04-P015 · 2 marksRf 6%, market return 12%, beta 1.25. Ke?
Explanation
Correct answer B: 13.5%.
6+1.25 x(12-6).
FM-C04-P016 · 2 marksRf 5%, already-stated market premium 8%, beta 1.1. Ke?
Explanation
Correct answer A: 13.8%.
5+1.1 x 8.
FM-C04-P017 · 2 marksConstant EPS 8, price 64. Model earnings-price rate?
Explanation
Correct answer D: 12.5%.
8/64; earnings are not automatic cash dividends.
FM-C04-P018 · 2 marksBuy 100, receive 10 at year 1, and 10 dividend plus 110 sale price at year 2. Historical IRR?
Explanation
Correct answer C: About 14.66%, not guaranteed future required return.
100=10/(1+k)+120/(1+k)^2; historical conditions need review.
FM-C04-P019 · 2 marksWeights debt 40%, preference 10%, equity 50%; costs 6%, 9%, 12% respectively. WACC?
Explanation
Correct answer D: 9.3%.
2.4+.9+6.
FM-C04-P020 · 2 marksMarket debt 30, preference 10, equity 100; costs 6%, 9%, 12%. WACC?
Explanation
Correct answer A: 10.5%.
(1.8+.9+12)/140.
FM-C04-P021 · 2 marksMarket equity 100 already includes retained claims. Add book retained 20 to market total?
Explanation
Correct answer B: No, that double counts the equity claim.
Market equity is one total unless an explicit allocation convention divides it once.
FM-C04-P022 · 2 marksRetention 18 lakh, target equity 60%. Total-funding breakpoint?
Explanation
Correct answer A: Rs 30 lakh.
18/.6.
FM-C04-P023 · 2 marksTarget debt 40% at 6%, equity 60% retained at 12%. MCC?
Explanation
Correct answer A: 9.6%.
.4 x 6+.6 x 12.
FM-C04-P024 · 2 marksSame target 40/60; debt 6%, external equity 14%. MCC?
Explanation
Correct answer D: 10.8%.
.4 x 6+.6 x 14.
FM-C04-P025 · 2 marksDebt capacity 15 lakh at low rate, target debt 50%. Total-funding breakpoint?
Explanation
Correct answer A: Rs 30 lakh.
15/.5.
FM-C04-P026 · 2 marksAfter-tax half-yearly IRR 3.5%. Effective annual rate?
Explanation
Correct answer B: 7.1225%.
1.035^2-1.
FM-C04-P027 · 2 marksForecast conversion shares value 120 versus cash redemption 100; supplied higher-value convention. Terminal model value before final coupon?
Explanation
Correct answer A: Rs 120, conditional and possibly non-cash.
Use choice once; forecast/option and economic-value assumptions matter.
FM-C04-P028 · 2 marksD1 positive but Ke 10%, g 12%. P=D1/(Ke-g) means what?
Explanation
Correct answer B: Invalid finite positive constant-growth valuation.
The perpetuity requires Ke>g.
FM-C04-P029 · 2 marksNPVs +2.01 at 8% and-1.78 at 9%. Linear estimate?
Explanation
Correct answer C: About 8.53%.
8+2.01/(2.01+1.78) percentage points; estimate only.
FM-C04-P030 · 2 marksDifferent-risk project uses company WACC without review. What is unsafe?
Explanation
Correct answer B: Treating that rate as automatically appropriate.
Company average is not a universal project hurdle.