Investment Decisions
Amounts are Rs lakh and ordinary share counts are lakh shares unless stated otherwise. 30 original test MCQs, 2 marks each. Practice and separate-test stems differ. T001-T010 use one shared case below; T011-T030 stand alone.
Original practice, not official ICAI questions or suggested answers. Scores are temporary and not synced to Study Hub. Contract/current-rule/accounting/tax boundaries are included in the review pack.
Not scored yet.
Cedar Components: shared case for T001-T010
Shared case: Cedar Components, T 001-T 010
Cedar considers one independent four-year project. At time 0, asset including installation costs Rs 100 lakh and net working capital requires Rs 10 lakh. Asset accounting/tax depreciation is straight-line Rs 20 lakh yearly, leaving taxbook/book residual Rs 20 lakh after year 4. Annual incremental sales are Rs 80 lakh and cash operating costs Rs 40 lakh. Corporate tax 25% is immediately payable/usable on the positive specified income. No financing interest or equity dividend is subtracted in these operating project cash flows; use matching discount rate 10%.
All operating receipts/payments occur at each yearend. At end year 4, sell the asset for Rs 20 lakh; the case's disposal tax model has no tax because sale equals taxbook. Working capital 10 is explicitly fully recovered then. No midlife capex, extra cash flows, inflation or loss-tax-relief uncertainties are included. All amounts are Rs lakh.
For strict dated cash recovery, only yearend receipts exist. If a question explicitly switches to conventional uniform operating cash within a year, label that different assumption and keep terminal extra 30 only at year 4. For ARR, use average asset capital=(100+20)/2 plus full WC 10 held throughout. Each first 10 question is independently scored, not dependent on a preceding answer. This is original practice, not current-law assurance or a purchase instruction.
FM-C07-T001 · 2 marksRead shared case
At time 0, total incremental project outlay?
Explanation
Correct answer A: 110 lakh.
Asset 100+WC 10.
FM-C07-T002 · 2 marksRead shared case
Annual accounting PAT?
Explanation
Correct answer D: 15 lakh.
(80-40-20)x.75.
FM-C07-T003 · 2 marksRead shared case
Annual operating cash flow?
Explanation
Correct answer A: 35 lakh.
PAT 15+depreciation 20.
FM-C07-T004 · 2 marksRead shared case
End year 4 total project cash flow?
Explanation
Correct answer C: 65 lakh.
OCF 35+sale 20+WC 10.
FM-C07-T005 · 2 marksRead shared case
At 10%, project NPV?
Explanation
Correct answer C: About 21.43569 lakh.
35 PVAF(10%, 4)+30/1.1^4-110.
FM-C07-T006 · 2 marksRead shared case
At 10%, PI?
Explanation
Correct answer C: About 1.194870.
PV 131.435694/outlay 110.
FM-C07-T007 · 2 marksRead shared case
ARR on specified average asset plus WC capital?
Explanation
Correct answer D: 21.4286%.
Average capital 60+10=70; PAT 15/70.
FM-C07-T008 · 2 marksRead shared case
Strict yearend receipts: when is cumulative investment recovered?
Explanation
Correct answer B: End year 4.
After 3 years 105<110; year 4 cash 65 reaches 170.
FM-C07-T009 · 2 marksRead shared case
Finance/reinvestment rates 10%; MIRR over 4 years?
Explanation
Correct answer B: About 15.0066%.
FV 35 x 1.1^3+35 x 1.1^2+35 x 1.1+65=192.435; (FV/110)^.25-1.
FM-C07-T010 · 2 marksRead shared case
Which appraisal statement is justified?
Explanation
Correct answer C: Positive NPV under stated cash/return; feasibility and risk need verification, not actual spending authorisation.
Independent value test positive; estimates/constraints remain case conditional.
FM-C07-T011 · 2 marksA road must be built if a factory is accepted. Appraisal treatment?
Explanation
Correct answer C: Include the necessary linked project cash flows and feasibility.
Contingent investments must be assessed together.
FM-C07-T012 · 2 marksRequired capex 20 at end year 2, discount 10%. Present cost?
Explanation
Correct answer A: 16.52893 lakh.
20/1.1^2.
FM-C07-T013 · 2 marksFull WC recovery is not established in a real proposal. Best treatment?
Explanation
Correct answer C: Verify amount/timing/impairment; do not promise recovery by textbook default.
Case recovery assumption is not evidence about real assets.
FM-C07-T014 · 2 marksA taxbook disposal loss arises but immediate usable relief is not verified. Treatment?
Explanation
Correct answer D: Hold timing/eligibility and use explicitly justified tax cash assumptions.
Block status, other assets and relief capacity can change cash effects.
FM-C07-T015 · 2 marksInitial 100, first two flows 30/40, third year 50 explicitly uniform. Conventional payback?
Explanation
Correct answer A: 2.6 years with that stated timing assumption.
After year 2 unrecovered 30; 30/50=.6.
FM-C07-T016 · 2 marksAnnual PAT 15, depreciation 20. Which numerator belongs to ARR?
Explanation
Correct answer B: 15 accounting profit, not 35 OCF.
ARR is accounting profit-based; cash models use cashflow.
FM-C07-T017 · 2 marksPV inflows equals outlay at appropriate discount return. What is established?
Explanation
Correct answer B: Zero NPV/value indifference, not zero cash receipts or automatic rejection.
PI 1; value criterion indifference under assumptions.
FM-C07-T018 · 2 marksFor A[-50, 70], B[-100, 130], incremental B-A IRR?
Explanation
Correct answer A: 20%.
Extra outlay 50/extra end cash 60; 60/50-1.
FM-C07-T019 · 2 marksA[-100, 140, 0], B[-100, 0, 160]. Crossover discount rate?
Explanation
Correct answer D: 14.2857%.
Equate 140/(1+r)=160/(1+r)^2.
FM-C07-T020 · 2 marksSame timing projects at 10%: higher NPV?
Explanation
Correct answer C: B 32.2314 versus A 27.2727, though A higher IRR.
PV later 160/1.1^2 versus earlier 140/1.1.
FM-C07-T021 · 2 marksFlows[-100, 230, -132], discount 15%. NPV?
Explanation
Correct answer B: About+.189036 lakh; check value directly despite two IRRs.
-100+230/1.15-132/1.15^2.
FM-C07-T022 · 2 marksNPV discounts cash at the required return. Which additional claim is unsafe?
Explanation
Correct answer D: Literal reinvestment of every receipt at that rate is necessary for the arithmetic NPV value.
Discount valuation and realised terminal reinvestment are different assertions; retain textbook discussion as a boundary.
FM-C07-T023 · 2 marksPI efficiency ordering is used to split a physically indivisible machine project. What is wrong?
Explanation
Correct answer B: Divisibility/linear proportional benefits were not established.
Discrete selection needs feasible combinations, not assumed fractions.
FM-C07-T024 · 2 marksBudget 100; A 60 NPV 30, B 50 NPV 26, C 50 NPV 25; C requires A. Which can no longer be assumed feasible?
Explanation
Correct answer D: B+C without A.
Dependency changes former independent-feasibility enumeration.
FM-C07-T025 · 2 marksOld cash cost 25/new 8; old dep 4/new 18; tax 25%. Incremental annual OCF?
Explanation
Correct answer D: 16.25 lakh.
17 x.75+(18-4)x.25=16.25.
FM-C07-T026 · 2 marksNew net residual 8/old net 4, WC increment 5 released. Terminal extra beyond annual OCF?
Explanation
Correct answer A: 9 lakh.
8-4+5.
FM-C07-T027 · 2 marksReal 30/year for 3 years, cost 70, real discount 10%. NPV?
Explanation
Correct answer B: 4.60556 lakh.
30 PVAF(10%, 3)-70.
FM-C07-T028 · 2 marksOutlay 110, 35 OCF for 3 years, terminal extra 28, 10%. Constant annual OCF for zero NPV?
Explanation
Correct answer D: 35.773414 lakh.
[110-28/1.1^3]/PVAF(10%, 3).
FM-C07-T029 · 2 marksScenario NPVs-20/+10/+40 probabilities.25/.5/.25. Probability of negative NPV in this model?
Explanation
Correct answer A: 25%, not zero just because expected NPV 10.
Only low case has negative NPV.
FM-C07-T030 · 2 marksUnequal-life choices cannot be repeated and terminal opportunities differ. Best comparison approach?
Explanation
Correct answer C: Use actual horizon/terminal options instead of imposing identical renewal cycles.
EAV/common chain requires appropriate horizon/repeatability facts.