CA INTER · AUDITING AND ETHICSAudit Strategy, Planning & Programme
30 independently written separate test scenario MCQs · 2 marks each
Includes audit strategy, audit planning and audit programme. These are original practice material, not ICAI past-paper questions, official suggested answers or an official marking scheme. One correct option per question. Scores are temporary and do not sync with Study Hub progress.
Not scored yet.
AUD-G02-T001 · 2 marksRadian Paints first identifies a difficult estimate on the planned signing day and discovers its specialist is unavailable. Which reason for early planning is most directly illustrated?
Explanation
Correct answer C: Identifying and addressing potential problems in good time.
Planning helps anticipate and deal with problems on time, including access to needed expertise. It does not guarantee an opinion or excuse missing relevant work.
AUD-G02-T002 · 2 marksPolaris Services has an experienced valuation senior and a new assistant. It assigns work randomly before considering expected risks. Which planning benefit could improve the allocation?
Explanation
Correct answer C: Selecting and assigning team members with capability suited to anticipated risks.
Adequate planning helps select competent members and assign work to respond to anticipated risks. Suitable assignment and supervision remain necessary.
AUD-G02-T003 · 2 marksNova Packaging waits until after identifying and assessing risks to consider materiality and possible expert involvement. Which assessment fits SA300 planning?
Explanation
Correct answer D: These are matters to consider in planning before that risk identification/assessment stage is complete.
Planning includes materiality, expert involvement, legal framework and risk assessment procedures. Considering expertise is not the same as mandating an expert in every case.
AUD-G02-T004 · 2 marksZenith Studios asks to arrange records and staff for the audit. The auditor refuses any timetable discussion, claiming all coordination is forbidden. Which is most accurate?
Explanation
Correct answer A: Planning elements may be discussed with management provided effectiveness is not compromised.
Logistical discussions can facilitate the audit. The requirement is to protect effectiveness, not to prohibit all management discussion or surrender procedure decisions.
AUD-G02-T005 · 2 marksAster Networks proposes a new engagement involving unfamiliar technical contracts. The audit firm knows little about the owners and has not assessed team skills. What preliminary work is relevant?
Explanation
Correct answer D: Obtain necessary information on client integrity, competence and engagement acceptance.
Acceptance/continuance procedures consider relevant integrity, competence and engagement issues. The facts call for assessment, not an assumed negative conclusion or automatic acceptance.
AUD-G02-T006 · 2 marksHelix Pharma identifies an independence threat and finds it cannot be adequately addressed. What should the partner do?
Explanation
Correct answer D: Take appropriate action, considering withdrawal where permitted and reporting an inability to resolve it to the firm.
The partner assesses independence and takes appropriate action on threats. Withdrawal is conditional on applicable law; unresolved matters should promptly go to the firm.
AUD-G02-T007 · 2 marksVega Foods has a fee quote but disagrees with the auditor about responsibilities and report expectations. Why clarify terms before audit commencement?
Explanation
Correct answer C: To avoid misunderstandings and identify circumstances affecting planning and performance.
Understanding terms is a preliminary activity that supports the ability to plan and perform. It does not predetermine the opinion or prove account balances.
AUD-G02-T008 · 2 marksRigel Electronics writes only detailed sample instructions and has no broad decision about scope, timing or direction. Which planning element is missing?
Explanation
Correct answer A: An overall audit strategy guiding the detailed plan.
Detailed steps do not replace the strategy's broad scope/timing/direction decisions. The strategy guides development of the audit plan.
AUD-G02-T009 · 2 marksSirius Distribution has high-risk warehouses and a straightforward office. Its budget divides audit hours equally for convenience. Which strategy consideration should replace that automatic rule?
Explanation
Correct answer D: Allocate amounts of resources to particular areas in light of their audit needs.
Strategy addresses numbers of staff and hours for areas, including material count locations and high-risk work. Equality is not a universal audit planning principle.
AUD-G02-T010 · 2 marksAltair Software needs expert input during estimate testing but plans the expert only for the report-signing evening. Which resource issue is most directly raised?
Explanation
Correct answer B: The timing of resource deployment must fit the work and evidence needs.
Strategy includes when resources are deployed. Expert involvement must be planned usefully; signing-day availability alone does not establish that needed work can be performed.
AUD-G02-T011 · 2 marksCapella Tools needs team briefings, debriefings and manager reviews across several sites. What does the strategy help determine?
Explanation
Correct answer D: How the resources will be directed, supervised and reviewed.
Strategy helps determine management of resources, including team meetings and partner/manager review. Staffing alone does not eliminate those needs.
AUD-G02-T012 · 2 marksArcturus Textiles uses a new reporting framework and has an unfamiliar business segment. Which input belongs in establishing strategy?
Explanation
Correct answer A: Engagement characteristics that define scope, including framework and specialised knowledge.
The strategy reflects framework and segment characteristics as well as reporting requirements and knowledge needs. Changes require assessment, not an automatic report conclusion.
AUD-G02-T013 · 2 marksProcyon Engineering's team assumes management wants only a final report; management expects earlier work-status updates and a draft discussion. What should be clarified when setting strategy?
Explanation
Correct answer D: Reporting objectives and the expected nature/timing of communications.
Reporting objectives inform timing, management discussions, status communications and team reviews. They are not limited to a final report date.
AUD-G02-T014 · 2 marksBetelgeuse Retail's earlier audit found a weak control. Management says it fixed the issue. How should the strategy use this information?
Explanation
Correct answer B: Consider previous findings and the action taken while assessing present relevance.
Previous control results and remediation are relevant planning inputs. A claim is not proof, and a prior weakness does not automatically establish current fraud.
AUD-G02-T015 · 2 marksSpica Logistics plans staff inquiries solely to understand operations and identify misstatement risks. Where should their nature, timing and extent be described?
Explanation
Correct answer C: In the risk assessment procedures part of the audit plan.
The stated purpose makes these planned risk assessment activities. Recording their planned detail does not turn them into proof of all account assertions.
AUD-G02-T016 · 2 marksAntares Services has assessed a risk affecting a year-end balance and is planning detailed work responsive to it. Which plan entry best describes that response?
Explanation
Correct answer B: Nature, timing and extent of further audit procedures at assertion level.
The plan needs a detailed assertion-level response. Bare headings and deadlines do not describe what work, when or how much is planned.
AUD-G02-T017 · 2 marksDeneb Health plans risk assessment and further tests but excludes a procedure required by an applicable SA because it is not on the high-risk list. What should happen?
Explanation
Correct answer C: Include the other required planned procedure so the engagement complies with SAs.
The audit plan includes other procedures needed for SA compliance as well as risk assessment and assertion-level work. A risk list does not waive applicable requirements.
AUD-G02-T018 · 2 marksRegulus Media has finished planning suitable work for income, while another area needs more understanding. Which statement about proceeding is accurate?
Explanation
Correct answer C: Suitable further work on income may begin while remaining planning develops.
Some further procedures can be performed before all remaining procedures are planned. This flexibility does not excuse neglect of other areas or later updates.
AUD-G02-T019 · 2 marksCastor Rentals calls strategy and plan entirely separate phases and refuses to alter the plan after changing the overall approach. Which view is correct?
Explanation
Correct answer D: They are closely related; a change in one may require changes in the other.
Strategy is the broad approach and the plan implements it in detail. They are not necessarily discrete sequential processes, nor does every change invalidate all prior work.
AUD-G02-T020 · 2 marksPollux Manufacturing asks its finance head to choose the auditor's strategy and detailed procedures. The auditor proposes adopting them without independent assessment. Which responsibility applies?
Explanation
Correct answer A: The overall strategy and audit plan remain the auditor's responsibility.
Management knowledge can aid coordination and understanding, but the auditor establishes strategy and develops the plan. Adopting management decisions uncritically transfers a responsibility that remains with the auditor.
AUD-G02-T021 · 2 marksFomalhaut Labs gets later evidence that conflicts with initial planning information. The partner considers a different approach and more experienced staff. What is appropriate?
Explanation
Correct answer A: Update strategy and plan as needed and revise the planned response to assessed risks.
Later evidence and changed conditions may require revisions to both approach and procedures. The effect on evidence and opinion still needs assessment.
AUD-G02-T022 · 2 marksAchernar Systems' simple payroll and complex estimate area have the same end-only review schedule. What should review planning consider?
Explanation
Correct answer B: Entity/area complexity, assessed risks and the competence of the people doing the work.
Direction, supervision and review vary with size/complexity, area, risks and staff capability. Uniform review is not automatically suitable.
AUD-G02-T023 · 2 marksAldebaran Crafts records a significant changed strategy but omits the reason. Which planning record is deficient?
Explanation
Correct answer A: Documentation of significant changes and why they were made.
Planning documentation covers the overall strategy, plan and significant changes with reasons. The rationale helps explain the final adopted response.
AUD-G02-T024 · 2 marksBellatrix Events hands assistants a written sequence of verification steps and suitable techniques for the financial statements. What is its main purpose?
Explanation
Correct answer B: To implement audit procedures that obtain sufficient evidence for an informed opinion.
The programme is detailed verification guidance for obtaining evidence. A programme or sign-off does not itself replace evidence or transfer management's preparation responsibility.
AUD-G02-T025 · 2 marksAlnilam Training's programme is copied from a stock-heavy retailer, although it provides only courses. What is the correct treatment of the template?
Explanation
Correct answer A: Tailor it to the actual business, controls and scope rather than use it unchanged.
Nature, size, composition and controls differ. A standard template can help but must be adapted to pertinent work and special circumstances.
AUD-G02-T026 · 2 marksAlnair Finance changes its collection process during the audit. The manager says the programme need never be reviewed once issued. Which response is correct?
Explanation
Correct answer C: Review programme adequacy periodically in light of operations and controls.
Periodic review keeps the programme useful, removing inadequacies and redundancies. This is a controlled revision process, not a licence for unilateral convenience deletions.
AUD-G02-T027 · 2 marksMirfak Tools thinks control reliance is always compulsory merely because a manual exists. No separate mandatory-testing issue is supplied. Which is best?
Explanation
Correct answer B: Consider controls and whether reliance or another approach obtains suitable evidence effectively and efficiently.
Programme construction reflects control assessment and results. Reliance may be useful, while other routes may be more efficient subject to applicable requirements; neither blanket extreme follows.
AUD-G02-T028 · 2 marksAlcyone Venues' programme separates deposit and rental-income work without considering linked contract evidence. What construction principle is relevant?
Explanation
Correct answer C: Coordinate procedures for related items while addressing relevant objectives.
Related items and evidence should be coordinated. Objectives, relevant procedures and error possibilities matter, rather than isolated checking or arbitrary quantities.
AUD-G02-T029 · 2 marksMizar Repairs has internal schedules and may obtain supplier information and inspect equipment. The manager calls only the existing schedules 'available evidence'. Which is accurate?
Explanation
Correct answer B: Availability is not limited to client-held records; consider obtainable relevant evidence and its weight.
Programme design identifies reasonably available evidence from various sources and weighs it for the assertion. External sources are not automatically sufficient, but the client folder is not the boundary.
AUD-G02-T030 · 2 marksDubhe Trading claims that a properly signed audit programme conclusively defeats any negligence allegation. Which is most accurate?
Explanation
Correct answer D: A properly drawn programme can have evidential value but is not automatic immunity.
A sound programme may help show reasonable care, but mechanical, obsolete or unsupported sign-offs do not conclusively establish audit performance. The actual work still matters.